Nicholas Recreation Center V2
Nicholas Recreation Center
project in Madison, WI.
Cost: $$65,871,200
Size: 250,800 sq. ft.
Completion Date: 2020

Summary: The Nicholas Recreation Center (Nick) is a new state-of-the-art facility where the Southeast Recreational Facility (the SERF building) used to be. The SERF building, one of UW Madison’s Rec Sports Facilities, was initially constructed in… read more.

Mmb
Madison Municipal Building
, , project in Madison, WI.
Cost: $30,200,00
Size: 74,880 sq. ft.
Completion Date: 2018

Summary: Home to many of Madison’s essential city employees and listed on the National Register of Historic Places, Madison’s Municipal Building, located at 215 Martin Luther King Jr Blvd, received some much-needed renovations in 2018. This… read more.

Uw Chemistry
UW Madison Chemistry Building Instructional Addition and Renovation
project in Madison, Wisconsin.
Cost: $133,100,000
Size: 245,840 sq. ft.
Completion Date: 2022

Summary: The project consists of the design and construction of a new eight-story undergraduate chemistry teaching tower, the renovation of existing undergraduate laboratories and offices in the Daniels portions of the existing Chemistry building, and the… read more.

UW Madison Sellery & Witte Residence Halls Renovation
project in Madison, Wisconsin.
Cost: $52,797,000
Size: 287,324 sq. ft.
Completion Date: 2019

Summary: Witte Residence Hall, which opened in 1964, was a two-tower structure that was home to 1,150 residents in double rooms. University Housing planned a major renovation to this building over a two-year span to address mechanical… read more.

UW Madison’s Meat Science and Animal Biologics Discovery Building
project in Madison, Wisconsin.
Cost: $36,088,175
Size: 72,784 sq. ft.
Completion Date: 2020

Summary: University of Wisconsin Madison's Meat Science and Animal Biologics Discovery (MSABD) building brings much-needed modernization to the school’s College of Agricultural and Life Sciences. The new MSABD building provides state-of-the-art teaching capabilities to train the… read more.

UIC Computer Research Design and Learning Center
project in Chicago, Illinois.
Cost: $76,336,168
Size: 135,000 sq. ft.
Completion Date: 2022

Summary: This project will construct a new four-story building to be primarily occupied by the University's Computer Science department. The new facility will include auditoriums and lecture halls, classrooms, dry laboratories, faculty and staff offices, student… read more.

UW Milwaukee Klotsche Center Annex Addition
project in Milwaukee, Wisconsin.
Cost: $5,927,091
Size: 17,342 sq. ft.
Completion Date: 2022

Summary: This project constructs a new one-court gymnasium with shell space for future multi-purpose and fitness and strength conditioning areas. It is anticipated that the addition will be located east of the Klotsche Center complex, which… read more.

UW Milwaukee Chemistry Building & Central Utilities Expansion
project in Milwuakee, Wisconsin.
Cost: $129,535,000
Size: 155,340 sq. ft.
Completion Date: 2022

Summary: This project constructs a new academic and research chemistry and bio-chemistry facility to provide instructional laboratories and associated support spaces, research laboratories, associated support spaces, offices, and shared collaboration/informal learning space. The project will also… read more.

University of Illinois at Chicago Engineering Innovation Building
project in Chicago, Illinois.
Cost: $31,893,950
Size: 57,500 sq. ft.
Completion Date: 2019

Summary: For students of the engineering, mechanical engineering, and civil engineering departments, the University of Illinois at Chicago's new Engineering Innovation Building provides many different research capabilities. The new 57,500 SF building features a state-of-the-art, four-story,… read more.

Illinois State Fair Coliseum
project in Springfield, Illinois.
Cost: $10,770,945
Size: 44,900 sq. ft.
Completion Date: 2019

Summary: Originally constructed in 1901 and listed on the National Register of Historic Places, “The Coliseum of Champions” at the Illinois State Fairgrounds has hosted many events, including concerts, horse shows, presidential rallies, and more. However,… read more.

Fort HealthCare Hospital
project in Fort Atkinson, WI.
Cost: $100,000,000
Size: 400,000 sq. ft.
Completion Date: 2019

Summary: Campus Regeneration Study: Provided Conceptual Cost Estimates for the potential re-location of a rural hospital. read more.

Debot Hall Dining Facility
project in Stevens Point, WI.
Cost: $10,000,000
Size: 56,820 sq. ft.
Completion Date: 2018

Summary: Provided Cost Estimating services for the study of the renovation for the Debot Hall Dining Facility at University of Wisconsin – Stevens Point. read more.

UW School of Engineering
project in Platteville, WI.
Cost: $60,000,000
Size: 400,000 sq. ft.
Completion Date: 2020

Summary: Provided Cost Estimating services and Value Engineering options for the renovation and additions to four academic buildings on the University of Wisconsin – Platteville campus. read more.

Prescott VA Medical Center
project in Prescott, AZ.
Cost: $3,400,000
Size: 2,000 sq. ft.
Completion Date: 2016

Summary: Provided Feasibility Studies and Cost Estimating services for the replacement of campus’ emergency power systems. read more.

Amarillo VA Medical Center
project in Amarillo, TX.
Cost: $8,000,000
Size: 45,000 sq. ft.
Completion Date: 2016

Summary: Provided Value Engineering and Cost Estimating services for all phases of the campus’ community based living center. read more.

Ann Arbor VA Medical Center
project in Ann Arbor, MI.
Cost: $7,800,000
Size: 40,000 sq. ft.
Completion Date: 2016

Summary: Provided Cost Estimating services and phasing review for the renovation and expansion of the facilities front entrance and outpatient clinic areas. read more.

UW Parking Expansion
project in La Crosse, WI.
Cost: $7,600,000
Size: 120,000 sq. ft.
Completion Date: 2016

Summary: The University of Wisconsin was granted permission to add two new levels to its new campus parking ramp. Provided Cost Estimating services and Scheduling input for the campus. read more.

UW Lacrosse Utility Building
project in Lacrosse, WI.
Cost: $2,500,000
Size: 6,540 sq. ft.
Completion Date: 2016

Summary: Provided Cost Estimating services for the addition and expansion of the chilled water plant at University of Wisconsin – Lacrosse. read more.

Epic Systems, Campus III
project in Verona, WI.
Cost: $200,000,000
Size: 400,000 sq. ft.
Completion Date: 2016

Summary: Provided Conceptual and Schematic Budgets for the Epic Campus III project. The project consisted of six office buildings and two underground parking facilities for the software developer. read more.

St. Joe’s Medical Center
project in Hobart, Indiana.
Cost: $23,000,000
Size: 60,000 sq. ft.
Completion Date: 2015

Summary: Provided Feasibility Studies and Cost Engineering Solutions for the expansion of the facilities operating and emergency departments. read more.

Madison VA ICU
project in Madison, WI.
Cost: $8,000,000
Size: 30,000 sq. ft.
Completion Date: 2015

Summary: Provided General Contracting services for the $8 Million ICU consolidation and expansion project. read more.

Milwaukee VA Medical Center
project in Milwaukee, WI.
Cost: $2,300,000
Size: 15,000 sq. ft.
Completion Date: 2015

Summary: Worked with the Owner and Contractor to provide cost loaded critical path schedules for the multi-phased prosthetics renovation. read more.

Milwaukee VA Generator
project in Milwaukee, WI.
Cost: $4,000,000
Size: 1,200 sq. ft.
Completion Date: 2015

Summary: This project consisted of the addition of Building 144’s Generator Facility. Provided Cost Estimating services. read more.

Syracuse VA Medical Center
project in Syracuse, NY.
Cost: $9,000,000
Size: 20,000 sq. ft.
Completion Date: 2015

Summary: Throughout the development and construction design phases of the 4th floor renovation of the community based living center,we provided Cost Estimating services. read more.

DNA Lab, Wisconsin DOJ
project in Madison, WI.
Cost: $5,100,000
Size: 20,000 sq. ft.
Completion Date: 2015

Summary: Provided pre-construction and construction level estimates for the renovation of the state of the art facility. read more.

UW Hospital Parking Ramp
project in Madison, WI.
Cost: $26,000,000
Size: 130,000 sq. ft.
Completion Date: 2015

Summary: This project consists of an expansion to the UW Hospital Parking Ramp with additions to the south and east side of the existing ramp. Engaged to provide Cost Estimating services. read more.

Green Bay Airport
project in Green Bay, WI.
Cost: $1,700,000
Size: 5,700 sq. ft.
Completion Date: 2015

Summary: Conducted pre-design feasibility and design estimates for the addition and renovation of the Green Bay International Airports Customs and Border Protection office. read more.

UW Whitewater Residence Halls
project in Whitewater, WI.
Cost: $12,000,000
Size: 108,000 sq. ft.
Completion Date: 2015

Summary: This project consisted of the renovation of multiple student residence buildings at University of Wisconsin - Whitewater dating from the mid 1960's with a focus on code and ADA compliance, circulation and student amenities. Provided… read more.

Hilldale Mall
project in Madison, WI.
Cost: $6,000,000
Size: 60,000 sq. ft.
Completion Date: 2015

Summary: Provided Cost Estimating and Value Engineering services for the multi-phased renovation and expansion of the retail mall. read more.

Tomah VA Medical Center
project in Tomah, WI.
Cost: $400,000
Size: 20,000 sq. ft.
Completion Date: 2014

Summary: Provided critical path schedules for the design team on the Water Meter Integration Project. read more.

Madison VA Medical Center
project in Madison, WI.
Cost: $10,000,000+
Size: In excess of 100,000 sq. ft.
Completion Date: 2014

Summary: Engaged by the design team. Provided critical path schedules on the various projects as part of the 2013 IDIQ. read more.

Madison VA IDIQ
project in Madison, WI.
Cost: $10,000,000
Size: in excess of 100,000 sq. ft.
Completion Date: 2014

Summary: Provided Cost Estimating services for $15 Million worth of projects during the 2013 IDIQ program. read more.

Wisconsin Veterans Home
project in Chain O’ Lakes-King, WI.
Cost: $3,400,000
Size: 2,000 sq. ft.
Completion Date: 2014

Summary: Provided Cost Estimating for the pedestrian circulation study, and subsequent addition and renovation of elevators at (4) of the campuses buildings. read more.

Milwaukee VA Fisher House
project in Milwaukee, WI.
Cost: $800,000
Size: 20,000 sq. ft.
Completion Date: 2014

Summary: Provided Value Engineering and Cost Estimating services for the civil and utility work required for the addition of the Fisher House. read more.

Manhattan Regional Airport
project in Manhattan, KS.
Cost: $12,000,000
Size: 24,000 sq. ft.
Completion Date: 2014

Summary: This $12 Million project included the expansion and renovation to the Manhattan Regional Airport. Provided Cost Estimating services, phasing and feasibly review. read more.

La Crosse Regional Airport
project in La Crosse, WI.
Cost: $1,300,000
Size: 60,000 sq. ft.
Completion Date: 2014

Summary: Provided Cost Estimating services and assisted in bid preparation for the exterior renovations and upgrades to the regional airport. read more.

McCalmont Residence Hall Renovation
project in Stout, WI.
Cost: $7,900,000
Size: 67,000 sq. ft.
Completion Date: 2014

Summary: This project at University of Wisconsin – Stout, included an addition and remodel of the freshman residence hall. Provided Cost Estimating and Value Engineering services. read more.

Airport Snow Removal Facility
project in Madison, WI.
Cost: $14,000,000
Size: 58,800 sq. ft.
Completion Date: 2013

Summary: This Green Certified building at the Dane County Regional Airport includes a new storage facility for the airport snow removal equipment and includes a geothermal heating/cooling system. Provided Cost Estimating services and a Foundations Cost… read more.

“Deep Space” Auditorium
project in Verona, WI.
Cost: $200,000,000
Size: 600,000 sq. ft.
Completion Date: 2013

Summary: This 11,000 seat auditorium project included preliminary schematic budgets and detailed quantity surveys for Epic System's “Deep Space” building. read more.

Fort HealthCare Operating Rooms
project in Fort Atkinson, WI.
Cost: $10,000,000
Size: 60,000 sq. ft.
Completion Date: 2010

Summary: This project included a renovation of the O/R rooms, labs and pharmacy area in the main hospital. Provided Cost Estimating, Budgeting and Change Order Review. read more.

Pike River Dormitory
project in Kenosha, WI.
Cost: $12,000,000
Size: 120,000 sq. ft.
Completion Date: 2009

Summary: Provided Cost Estimating and Bidding services to the general contractor for the Pike River Suites Dormitory at University of Wisconsin – Parkside. Additionally, we provided value engineering options to the Owner and Architect to bring… read more.