Fort HealthCare Hospital
project in Fort Atkinson, WI.
Cost: $100,000,000
Size: 400,000sq. ft
Completion Date: In progress

Summary: Campus Regeneration Study: Provided Conceptual Cost Estimates for the potential re-location of a rural hospital.

Debot Hall Dining Facility
project in Stevens Point, WI.
Cost: $10,000,000
Size: 56,820sq. ft
Completion Date: 2017-2018

Summary: Provided Cost Estimating services for the study of the renovation for the Debot Hall Dining Facility at University of Wisconsin – Stevens Point.

UW School of Engineering
project in Platteville, WI.
Cost: $60,000,000
Size: 400,000sq. ft
Completion Date: 2017-2020

Summary: Provided Cost Estimating services and Value Engineering options for the renovation and additions to four academic buildings on the University of Wisconsin – Platteville campus.

Prescott VA Medical Center
project in Prescott, AZ.
Cost: $3,400,000
Size: 2,000sq. ft
Completion Date: 2016

Summary: Provided Feasibility Studies and Cost Estimating services for the replacement of campus’ emergency power systems.

Amarillo VA Medical Center
project in Amarillo, TX.
Cost: $8,000,000
Size: 45,000sq. ft
Completion Date: 2016

Summary: Provided Value Engineering and Cost Estimating services for all phases of the campus’ community based living center.

Ann Arbor VA Medical Center
project in Ann Arbor, MI.
Cost: $7,800,000
Size: 40,000sq. ft
Completion Date: 2016

Summary: Provided Cost Estimating services and phasing review for the renovation and expansion of the facilities front entrance and outpatient clinic areas.

UW Parking Expansion
project in La Crosse, WI.
Cost: $7,600,000
Size: 120,000sq. ft
Completion Date: 2016

Summary: The University of Wisconsin was granted permission to add two new levels to its new campus parking ramp. Provided Cost Estimating services and Scheduling input for the campus.

UW Lacrosse Utility Building
project in Lacrosse, WI.
Cost: $2,500,000
Size: 6,540sq. ft
Completion Date: 2016

Summary: Provided Cost Estimating services for the addition and expansion of the chilled water plant at University of Wisconsin – Lacrosse.

Epic Systems, Campus III
project in Verona, WI.
Cost: $200,000,000
Size: 400,000sq. ft
Completion Date: 2016

Summary: Provided Conceptual and Schematic Budgets for the Epic Campus III project. The project consisted of six office buildings and two underground parking facilities for the software developer.

St. Joe’s Medical Center
project in Hobart, Indiana.
Cost: $23,000,000
Size: 60,000sq. ft
Completion Date: 2015

Summary: Provided Feasibility Studies and Cost Engineering Solutions for the expansion of the facilities operating and emergency departments.

Madison VA ICU
project in Madison, WI.
Cost: $8,000,000
Size: 30,000sq. ft
Completion Date: 2015

Summary: Provided General Contracting services for the $8 Million ICU consolidation and expansion project.

Milwaukee VA Medical Center
project in Milwaukee, WI.
Cost: $2,300,000
Size: 15,000sq. ft
Completion Date: 2015

Summary: Worked with the Owner and Contractor to provide cost loaded critical path schedules for the multi-phased prosthetics renovation.

Milwaukee VA Generator
project in Milwaukee, WI.
Cost: $4,000,000
Size: 1,200sq. ft
Completion Date: 2015

Summary: This project consisted of the addition of Building 144’s Generator Facility. Provided Cost Estimating services.

Syracuse VA Medical Center
project in Syracuse, NY.
Cost: $9,000,000
Size: 20,000sq. ft
Completion Date: 2015

Summary: Throughout the development and construction design phases of the 4th floor renovation of the community based living center,we provided Cost Estimating services.

DNA Lab, Wisconsin DOJ
project in Madison, WI.
Cost: $5,100,000
Size: 20,000sq. ft
Completion Date: 2015

Summary: Provided pre-construction and construction level estimates for the renovation of the state of the art facility.

UW Hospital Parking Ramp
project in Madison, WI.
Cost: $26,000,000
Size: 130,000sq. ft
Completion Date: 2015

Summary: This project consists of an expansion to the UW Hospital Parking Ramp with additions to the south and east side of the existing ramp. Engaged to provide Cost Estimating services.

Green Bay Airport
project in Green Bay, WI.
Cost: $1,700,000
Size: 5,700sq. ft
Completion Date: 2015

Summary: Conducted pre-design feasibility and design estimates for the addition and renovation of the Green Bay International Airports Customs and Border Protection office.

UW Whitewater Residence Halls
project in Whitewater, WI.
Cost: $12,000,000
Size: 108,000sq. ft
Completion Date: 2015

Summary: This project consisted of the renovation of multiple student residence buildings at University of Wisconsin – Whitewater dating from the mid 1960’s with a focus on code and ADA compliance, circulation and student amenities. Provided Cost Estimating services through all phases of work. Additionally, we provided Value Engineering services.

Hilldale Mall
project in Madison, WI.
Cost: $6,000,000
Size: 60,000 sq. ft
Completion Date: 2015

Summary: Provided Cost Estimating and Value Engineering services for the multi-phased renovation and expansion of the retail mall.

Tomah VA Medical Center
project in Tomah, WI.
Cost: $400,000
Size: 20,000sq. ft
Completion Date: 2014

Summary: Provided critical path schedules for the design team on the Water Meter Integration Project.

Madison VA Medical Center
project in Madison, WI.
Cost: $10,000,000+
Size: In excess of 100,000sq. ft
Completion Date: 2014

Summary: Engaged by the design team. Provided critical path schedules on the various projects as part of the 2013 IDIQ.

Madison VA IDIQ
project in Madison, WI.
Cost: $10,000,000
Size: in excess of 100,000sq. ft
Completion Date: 2014

Summary: Provided Cost Estimating services for $15 Million worth of projects during the 2013 IDIQ program.

Wisconsin Veterans Home
project in Chain O’ Lakes-King, WI.
Cost: $3,400,000
Size: 2,000sq. ft
Completion Date: 2014

Summary: Provided Cost Estimating for the pedestrian circulation study, and subsequent addition and renovation of elevators at (4) of the campuses buildings.

Milwaukee VA Fisher House
project in Milwaukee, WI.
Cost: $800,000
Size: 20,000sq. ft
Completion Date: 2014

Summary: Provided Value Engineering and Cost Estimating services for the civil and utility work required for the addition of the Fisher House.

Manhattan Regional Airport
project in Manhattan, KS.
Cost: $12,000,000
Size: 24,000sq. ft
Completion Date: 2014

Summary: This $12 Million project included the expansion and renovation to the Manhattan Regional Airport. Provided Cost Estimating services, phasing and feasibly review.

La Crosse Regional Airport
project in La Crosse, WI.
Cost: $1,300,000
Size: 60,000sq. ft
Completion Date: 2014

Summary: Provided Cost Estimating services and assisted in bid preparation for the exterior renovations and upgrades to the regional airport.

McCalmont Residence Hall Renovation
project in Stout, WI.
Cost: $7,900,000
Size: 67,000sq. ft
Completion Date: 2014

Summary: This project at University of Wisconsin – Stout, included an addition and remodel of the freshman residence hall. Provided Cost Estimating and Value Engineering services.

Airport Snow Removal Facility
project in Madison, WI.
Cost: $14,000,000
Size: 58,800sq. ft
Completion Date: 2013

Summary: This Green Certified building at the Dane County Regional Airport includes a new storage facility for the airport snow removal equipment and includes a geothermal heating/cooling system. Provided Cost Estimating services and a Foundations Cost Analysis.

“Deep Space” Auditorium
project in Verona, WI.
Cost: $200,000,000
Size: 600,000sq. ft
Completion Date: 2013

Summary: This 11,000 seat auditorium project included preliminary schematic budgets and detailed quantity surveys for Epic System’s “Deep Space” building.

Fort HealthCare Operating Rooms
project in Fort Atkinson, WI.
Cost: $10,000,000
Size: 60,000sq. ft
Completion Date: 2010

Summary: This project included a renovation of the O/R rooms, labs and pharmacy area in the main hospital. Provided Cost Estimating, Budgeting and Change Order Review.

Pike River Dormitory
project in Kenosha, WI.
Cost: $12,000,000
Size: 120,000sq. ft
Completion Date: 2009

Summary: Provided Cost Estimating and Bidding services to the general contractor for the Pike River Suites Dormitory at University of Wisconsin – Parkside. Additionally, we provided value engineering options to the Owner and Architect to bring the project costs in line with the approved budget.